Project Documents

This page contains study documents for the transportation improvements within the Eastern Corridor Segments II and III study area (Red Bank to I-275/SR 32).  To review community meeting materials pertaining to this effort, please go to the Public Involvement page.


EASTERN CORRIDOR SEGMENTS II and III TRANSPORTATION NEEDS ANALYSIS FINAL REPORT (JULY 2017)
This report provides the results of the transportation needs analysis prepared for Segments II and III of the Eastern Corridor Program in 2016 and 2017. Needs were identified through technical studies (traffic volume, travel time, congestion and crash data) as well as stakeholder input. Information from the report will be used to help develop solutions to the transportation needs identified.

Segments II and III Transportation Needs Analysis Report (JULY 2017) – FINAL 

Appendices 1 through 6
Appendices

Attachment A: Technical Studies
Attachment A1: ODOT Certified Traffic
Attachment A2: Crash Data
Attachment A3: HCS Data
Attachments A4 and A5: Travel Time Data and Geometric Data

Attachment B: Stakeholder Input
Attachment B1: Public Involvement Plan
Attachment B2: Eastern Corridor Development Team (ECDT) Meeting Summary and Materials
Attachment B3: Summaries of Focus Area Workshops

Attachment B4: Internet Survey, Public Feedback Summary Report
Attachment B5: March 9, 2017 Public Open House Summary Report

Attachment C: Other Transportation Modes
Attachments C1 and C2: Inventory of Existing and Proposed Bike Trails and SORTA Bus Routes


EASTERN CORRIDOR SR 32 RELOCATION (SEGMENTS II/III) (AUGUST 2015)
STATUS UPDATE AND RECOMMENDATIONS FOR FURTHER PROJECT DEVELOPMENT

This document outlines ODOT’s recommendations and related rationale for a revised approach to the SR 32 Relocation project.  It also summarizes the findings of project-related activities, coordination efforts and assessments completed between June 2013 and July 2015, upon which ODOT’s recommendations are based.

Status Update and Recommendations for Further Project Development


SR 32 RELOCATION SITUATION ASSESSMENT (NOVEMBER 2014)
Completed as part of the SR 32 Relocation project’s collaborative process, the Situation Assessment report summarizes the varying perspectives of just over 100 project stakeholders and offers a set of possible options for moving forward. Information from this report will be used to further inform the project development process.

SR 32 Relocation Project Situation Assessment Report, (November 2014)


SR 32 FEASIBILITY STUDY ADDENDUM (DECEMBER 2012)
The SR 32 Relocation Feasibility Study Addendum clarifies and updates the March 2012 report to take into account public comments and agency input received after the SR 32 Relocation public involvement meeting held August 2, 2012. Updated recommendations have been incorporated into the project development process.

Feasibility Study Addendum (December 2012)

Revised Figure 12 – History Architecture Resources (December 2012)

Revised Figure 17 – Alternative Corridors Recommended for Advancement (December 2012)


SR 32 RELOCATION FEASIBILITY STUDY (MARCH 2012)
The Feasibility Study, following ODOT’s new Project Development Process (PDP), evaluates the preliminary alternatives carried over from Tier 1 (see the Tier 1 DEIS) and makes recommendations about corridors to be advanced for further study – as shown on Revised Figure 17 – Alternative Corridors Recommended for Advancement. No decisions on the location of specific alignments or a preferred alternative have been made. The corridors depicted on all of the maps in the Feasibility Study are preliminary, some of which have been eliminated from further consideration by the Feasibility Study, or continue to be refined. Preliminary impacts reported in the Feasibility Study were calculated for broad corridors, and will also continue to be updated as alternatives are refined and avoidance and minimization measures are further developed.

Information included in the Feasibility Study was presented for public review at a Public Involvement Meeting held on August 2, 2012. Click here to review materials presented at that meeting and notes from the Question and Answer session.

Eastern Corridor Segment II-III Feasibility Study Report
(Figures 1, 2 and 7 are located within the report above)

Figure 3 – Project Location
Figure 4 – Study Area Subareas & Alternatives
Figure 5 – Typical Sections
Figure 6 – Community & Land Use Features
Figure 8 – Potential Displacements
Figure 9 – Floodplain and Floodway
Figure 10 – Drinking Water Resources
Figure 11 – Ecological Resources
Figure 12 – History Architecture Resources
Figure 13 – Archaeological Sensitivity
Figure 14 – Public Parks and Greenspaces
Figure 15 – Hazardous Materials Concerns
Figure 16 – Engineering and Design Considerations
Figure 17 – Alternative Corridors Recommended for Advancement
Figure 18 – Recommended Alternative Corridors with Environmental Features
Table 11 – US 50-Red Bank Subarea Matrix
Table 12 – River Crossing Subarea Matrix
Table 13 – River Plains Subarea Matrix
Table 14 – Newtown Subarea Matrix
Table 15 – Mt Carmel Subarea Matrix
References

Appendix A Record of Decision
Appendix A – Record of Decision

Appendix B Eastern Corridor Land Use Vision Plan and Green Infrastructure Master Plan
Appendix B1 – 2002 Land Use Vision Plan Summary Excerpts

Appendix B2 – 2005 Green Infrastructure Master Plan Summary

Appendix C Eastern Corridor Tier 1 Purpose and Need
Appendix C1 – Eastern Corridor Tier 1 Purpose and Need

Appendix C2 – Eastern Corridor Tier 1 Purpose and Need Exhibits
Appendix D – EC Tier 1 Environmental Commitments
Appendix E Eastern Corridor Tier 1 No Build

Appendix F Environmental Resources Support Materials
Appendix F1 – Soil and Bedrock Mapping and Archived Geological Data

Appendix F2 – Environmental Justice
Appendix F3 – OEPA Drinking Water Map
Appendix F4 – Detailed Ecological Mapping

Appendix G Cost Estimates
Appendix G1 – Construction Cost Estimates

Appendix G2 – ROW Cost Estimates

Appendix H Public Involvement
Appendix H1 – Meeting Minutes – Local Jurisdiction Meetings (2008)

Appendix H2 – Land Use Vision Plan Update Summary (2009)
Appendix H3 – Segment II-III Public Involvement Plan (2011)
Appendix H4 – Tribal Coordination Summary (2011)

Appendix I Supporting Studies (these files are all large and may require additional download time)
Appendix I1 – Ecological Resources Inventory Report (2008)

Appendix I2 – Environmental Site Assessment Screening (2008)
Appendix I3 – LMR Hydraulics Phase 1 (2009)
Appendix I3 – LMR Hydraulics Phase 2 (2009)
Appendix I4 – LMR Geomorphology Phase 1 (2009)
Appendix I4 – LMR Geomorphology Phase 2 (2009)
Appendix I5 – History-Architecture Red Flag Summary (2009)
Appendix I6 – Archaeological Modeling Study (2009)
Appendix I7 – Preliminary Noise Screening Report (2009)
Appendix I8 – Archaeology Literature Review and Disturbance Report (2010)
Appendix J Interactive PDF


Other Documents and Quick Links

SR 32 Relocation Project Status
SR 32 Relocation Fact Sheet
SR 32 Relocation FAQs
OKI Traffic Demand Model Fact Sheet
OKI Traffic Demand Model Description
Section 106 Consultation
Section 106 Consulting Parties Application